How Planning Permission Works in Ireland: Steps, Timeline and Fees

Last updated:

If your project is not exempt, you need planning permission from your local council before you build. The process is the same in every county and usually takes about three months from newspaper notice to final grant, longer if the council asks for more information or someone appeals.

Get your project checked

Step by step

For a typical house extension or alteration, the statutory process runs like this:

  • Publish a notice in an approved local newspaper and put up a site notice that can be read from the road.
  • Lodge the application with the council within two weeks of the newspaper notice, with drawings, maps and the fee.
  • For the first five weeks, anyone can make a submission or objection (the fee for an observer is €20). Your site notice must stay up and readable for these five weeks.
  • The council decides within eight weeks of receiving the application, or asks for further information.
  • If it asks for further information, it has four weeks from your response to decide.
  • Anyone who made a submission, or you as the applicant, can appeal to An Coimisiún Pleanála within four weeks of the decision.
  • If there is no appeal, the council issues the final grant of permission.

What it costs in council fees

Council application fees are set nationally, so they are the same in every county:

  • House extension, garage conversion or other works to an existing house: €34.
  • A new house: €65.
  • Retention of an extension or other domestic works already built: €102, or €2.50 per m², whichever is greater.
  • Retention of a house: €195, or €2.50 per m², whichever is greater.
  • A Section 5 declaration that works are exempt: €80.

The real cost is the drawings

The council fee is small next to professional fees for site maps, drawings, notices and any engineering input. Some permissions also attract development contributions set by the council’s own scheme, often charged on floor area above the exempt threshold. Ask for all of this to be quoted in writing up front.

Most applications fail on paperwork first

Councils reject applications as invalid before considering them if the notices are wrong, the site notice is not visible, drawings are missing or the newspaper is not on the approved list. An invalid application means starting again with new notices. This is where professional preparation saves the most time.

Check if you need permission at all

Since 27 July 2026 more home projects are exempt, including rear extensions up to 45 m², side and rear dormers and larger garden buildings. If your project fits an exemption, you may only need a Section 5 declaration (€80) instead of a full application.

Your checklist before starting

  • Check whether your project is exempt under the 2026 rules.
  • Review the planning history of the property and estate.
  • Get drawings, site maps and notices prepared professionally.
  • Publish the newspaper notice, erect the site notice and lodge within two weeks.
  • Respond quickly and fully to any further information request.
  • Wait four weeks after the decision for the appeal period before starting work.

Common questions

How long does planning permission take in Ireland?

The council must decide within eight weeks of a valid application. With the four-week appeal period and final grant, plan for about three months. A further information request or an appeal adds more time.

How much does planning permission cost for an extension?

The council fee is €34. Professional fees for drawings and the application are separate and vary by project.

Can I start work once the council grants permission?

Wait until the final grant issues after the four-week appeal period, and comply with any conditions that must be met before work starts. Building Control rules may also require a Commencement Notice.